Excavation Shoring Completed for Seattle Project

Staff -- Pacific Builder and Engineer, 11/6/2006

Seattle— DBM Contactors Inc. recently completed the excavation shoring for Olive 8, a 36-story condominium-hotel project in downtown Seattle at the corner of 8th Avenue and Olive Way. The project owner is R.C. Hedreen and the general contractor is Skanska USA.

The complex excavation shoring project was done on a site measuring 241 feet by 110 feet in a congested downtown location. It consisted of installing 100 soldier piles averaging 80 feet deep, 20 of which are underpinning the existing foundation wall of the Paramount Hotel.

For the west alley wall, 660 soil nail anchors and 8,900 square feet of 6-inch reinforced shotcrete shoring were installed until reaching the bottom of the neighboring Qwest building foundation. Tieback anchors and timber lagging complete the shoring from the base of the shotcrete to the bottom of excavation. A total of 560 tieback anchors and 38,000 square feet of timber lagging were installed to complete the shoring system.

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

Sponsored Links

 
Advertisement
Click Go for full forecast

More Content

  • Blogs
  • Photos

Blogs


Sorry, no blogs are active for this topic.

View All Blogs RSS

Photos

Advertisements





e-newsletters

Click to sign-up now for ACP’s free newsletters.

Construction eWire Canada
Construction eWire US
Heavy Construction Weekly
Executive Insights
Design & Cost
About Us   |   Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   FREE Subscription   |   RSS
© 2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites