Restoring I-64 In Louisville

Fast-paced project gives needed repairs to expressway built during the late 1960s

Story by Tom Hale -- Construction Digest, 9/10/2007

The Kentucky Transportation Cabinet's Restore 64 project, involving the restoration of Interstate 64 (Riverside Expressway) along the riverfront in downtown Louisville, Ky., is now complete, and the newly resurfaced lanes are open to traffic. Contractor Gohmann Asphalt & Construction Inc., Clarksville, Ind., put finishing touches to this $53-million, fast-track project in late July, a week ahead of schedule.

Chief District 5 Engineer Matt Bullock says although the project took a lot of manpower, planning and coordination, it was worth the effort. "Restore 64 has been a huge success," he states. "We are extremely happy with the timely progress construction crews made on this enormous project."

Phase 1 of Restore 64 took place during weekends in June. Then, in early July, Riverside Expressway was closed to all traffic between 3rd and 22nd streets as contractors proceeded with Phase 2 of the project. That closure remained in effect during the next three weeks.

For Restore 64, crews worked around-the-clock to repair and resurface 21 lane miles of highway, repair 132 expansion joints, construct new barrier walls, repair structural steel components, and replace overhead signs. Major repairs had not been performed on I-64 since its construction 40 years ago. And the wear and tear of approximately 100,000 cars and trucks a day had taken its toll on the interstate.

According to District 5 Construction Engineer Chris Poe, a total of 78,133.14 tons of asphalt (including base, level and wedge, and Rosphalt) were placed during Restore 64.

Innovative Approach

The Kentucky Transportation Cabinet has been taking some innovative approaches to highway projects in an effort to limit the impact on drivers, decrease construction zone accidents and save costs. Examples include working only at night, on weekends, or closing the road to complete the job quickly.

Shutting down I-64 was determined to be the most efficient and cost-effective method of tackling Restore 64. The closure allowed crews to work in a safe, uninterrupted environment. It also saved taxpayers the cost of an extended construction season that would have normally closed a few lanes at a time and would have lasted months.

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

There are no other articles written by this author.

Sponsored Links

 
Advertisement

More Content

  • Blogs
  • Photos

Blogs

  • Loren Faulkner
    California Builder and Engineer

    April 1, 2009
    California: According to the Construction Stats
    Once again the actual heavy/highway construction permits recorded in the past 30 to 60 days up and down the State of California show the rather ane......
    More
  • Tom Hale
    Construction Digest

    March 27, 2009
    Improving Traffic-Choked Indiana Corridor
    Easily the worst area to travel in Indianapolis is near Interstate 465 and I-69 just northeast of the city. It is a major bottleneck, especially&nb......
    More
  • View All BlogsRSS

Photos






e-newsletters

Click to sign-up now for ACP’s free newsletters.

eWire Canada
eWire
Heavy Construction Weekly
Executive Insights
Design & Cost
Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   RSS
© 2009 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites