Week 28 by Ivy Chang -- Associated Construction Publications, 2/22/2008

At the bridge site, Flatiron-Manson crews are pouring concrete on the top third of Pier 2 northbound, the middle third of Pier 2 southbound, the bottom third of Pier 3 northbound, and the middle third of Pier 4 southbound. By the first week in March, all piers should be completed.
Pouring first precast segments
Left: A construction crew pours one of the first precast segments of the main bridge in the casting yard in mid-February. Photo courtesy of Figg Engineering.


Foundation shafts completed, shoring work begins

On Wednesday, February 13, the last of 40 foundation shafts for footings of the Second Street Bridge were drilled, and crews are fabricating and placing rebar cages into the shafts. They will pour concrete into the footings next week.

Crews also began shoring work for the 40-foot retaining walls that will be placed beside freeway entrance and exit ramps at University Avenue. The shoring operation includes excavating the area and placing steel supports in the ground and will require about a week to complete. Work on the walls will take place around the clock until early spring.

Smoothing the top of a roadway on precast segmentAfter concrete is poured, a worker smoothes the top of the roadway on the precast segment. Photo courtesy of Figg Engineering.

More public information available

Cranes will lift heavy steel components and will be operating during the day. Throughout the next few months, people will notice additional hammering noise as crews build temporary support structures on both sides of the Mississippi River.

At the MSP International Airport, a touch-screen kiosk on Concourse C has been installed, MnDOT included new information about Smart Bridge technology and cold weather construction on its website at www.mndot.gov, and two webcams are now showing the progress of the bridge construction.

House approves victims’ compensation bill

On February 18, a Minnesota House committee approved a bill to compensate victims of the Interstate 35W bridge collapse. The bill proposes to set up a catastrophe fund modeled after the September 11 victims’ compensation package that Congress passed in 2001.

The fund will remain in place for future catastrophes and could be refilled by the Legislature. It covers compensation for lost wages, medical expenses, burial costs, and other expenses not covered by other sources.

Claimants would agree not to sue the state and they would not be subject to a $300,000 state liability cap. The Democratic representative and author of the bill estimates that the fund would have between $30 million to $60 million to meet claims of bridge victims. The bill was referred to the House Public Safety and Civil Justice Committee.

A Democratic state senator intends to introduce a similar bill that would cap claims at $400,000. He and another House member also are working on an amendment to bar lawyers from recovering fees from the fund.

The House member was skeptical of a fund that covers some of the losses that insurance companies already cover when liability for the bridge collapse has not been determined. In addition, he added, who determines which tragedy qualifies for special compensation in the future and how many funds does the Legislature establish?

Auditor releases report on Minnesota’s road spending

The next day, Minnesota’s Legislative Auditor released a 105-page report on the state’s transportation system that says without new money, Minnesota won’t be able to do more than maintain current roadways, and borrowing money for transportation is not enough. Minnesota also had more miles of trunk highway in poor condition in 2007 than five years before when the Minnesota Department of Transportation had 19 percent fewer employees.

MnDOT had a policy of preservation first, according to the report, but more than half of the agency’s trunk highway spending was on expansion projects in the past five years and, when adjusted for inflation, tax revenues for trunk highways decreased since 2003. The result was MnDOT committed more money for road construction and less on operations, research and support.

Regarding MnDOT’s bridge work, the report said the agency was completing high-priority bridge repairs, but was falling behind on routine maintenance. The auditor urged legislators of both parties to reach a compromise on transportation funding and show some improvement in their rapport.

         

           

 

Email
Print
Reprint
Learn RSS

Related Content

Related Content

 

By This Author

There are no other articles written by this author.

Sponsored Links

 
Advertisement

More Content

  • Blogs
  • Photos

Blogs

  • Carl Molesworth
    Pacific Builder and Engineer

    March 25, 2009
    Construction Could Lose in Colorado Funding Fight
    I was tempted to title this entry “Easy Come, Easy Go.” But in politics, nothing is easy when money is involved. The C......
    More
  • Carl Molesworth
    Pacific Builder and Engineer

    March 9, 2009
    Consensus Reached on I-5 Columbia River Bridge Replacement
    With all the attention on the federal stimulus funding over the past few weeks, this story nearly slipped past me. The Columbia River Cros......
    More
  • View All BlogsRSS

Photos






e-newsletters

Click to sign-up now for ACP’s free newsletters.

eWire Canada
eWire
Heavy Construction Weekly
Executive Insights
Design & Cost
Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   RSS
© 2009 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites