Focus on Crane Safety

Pre-planning with a scale drawing identifies potential issues.

By Greg Pantaleo, The Beck Group -- Construction News, 9/1/2008

Moving materials on the job site in an efficient and safe manner is often the prime driver of the project schedule. The selection and placement of hoisting equipment is critical to our success. Whether we are renting and operating the crane directly or turnkeying the entire structure package, we, as the controlling contractor, must conduct a detailed study of the proposed equipment.

None of us can afford idle hooks on a job; it is an intuitive notion that an idle crane wastes money. The cost of not enough crane for the job can be difficult to calculate, but undoubtedly it is equally if not more costly. The obvious effect of too little crane for the job is schedule impact. The not so obvious costs include extended hours, tired operators, cutting corners on rigging in the name of speed, and safety-related issues from trying to do too much with too little, not to mention unhappy subcontractors, poor morale, and back charges that can follow.

A simple way to study a subcontractor's crane choice is for you and your sub to draw a scale drawing of the crane at the first and last elevated deck with a typical load in place.

Using this process I've identified numerous potential issues. One such example follows: I've found with the scale drawing that a mobile crane that safely moved 100-foot tables at lower elevations is boom blocked by its own load at top floors. It was physically possible to set these tables, but with the boom angle so steep and load so close to the tip of the boom, the tables could rotate and strike the boom in windy conditions.

Another easy mistake is charting a crane for building height with standard rigging, then failing to consider the longer rigging required for precast, glass and other building skins. When this happens, contractors have to take the materials over the building perimeter and roads, as opposed to the relative safety of traveling over the structure. These drawings, charts and studies should be kept in the JHA (Job Hazard Analysis) section of your Job Safety Files.

It is imperative that all superintendents and project managers get involved in a subcontractor's choice of cranes. While we don't want to mandate all means and methods, we can and should mandate that enough crane is supplied to complete the job safely.

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

There are no other articles written by this author.

Sponsored Links

 
Advertisement
Click Go for full forecast

More Content

  • Blogs
  • Photos

Blogs

  • Loren Faulkner
    California Builder and Engineer

    November 19, 2008
    One More Try…
    If you own off-road diesel construction equipment in California you have one more shot at slowing down passage of the California Air Resources Boar......
    More
  • Loren Faulkner
    California Builder and Engineer

    November 11, 2008
    Coming To A Freeway Near You (maybe)…
    There are 600-plus electronic billboards that line California’s freeways to bring us the occasional Amber Alert or warn of traffic accidents ......
    More
  • View All BlogsRSS

Photos

Advertisements





e-newsletters

Click to sign-up now for ACP’s free newsletters.

Construction eWire Canada
Construction eWire US
Heavy Construction Weekly
Executive Insights
Design & Cost
About Us   |   Advertising Info   |   Site Map   |   Contact Us   |   Useful Sites   |   FREE Subscription   |   RSS
© 2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites