NEW BRIDGE CONSTRUCTION
ID - B -42579-A
ID - B -42579-A
Location: IN MARSHALL County 640 District
Bid Date/Time: Feb. 10, 2023, 10 a.m.
Project Type:
Bridge
Status: Awarded
Description:
NEW BRIDGE CONSTRUCTION ON US 31 OVER ELKHART WESTERN RAILROAD, 4.80 MILES SOUTH OF US 30
NEW BRIDGE CONSTRUCTION ON US 31 OVER ELKHART WESTERN RAILROAD, 4.80 MILES SOUTH OF US 30
Project Roles
Owners
- Owner INDIANA DEPARTMENT OF TRANSPORTATION, 100 NORTH SENATE AVENUE INDIANAPOLIS IN 46204
Bidders
- Bidder PHEND & BROWN, INC., - $28,781,892, 367 E 1250 N P O BOX 150 MILFORD IN 46542
- Bidder MILESTONE CONTRACTORS LP, - $29,943,216, 5757 Decatur Blvd, Suite 250 INDIANAPOLIS IN 46241
- Bidder ICC GROUP INC., - $33,705,000, 39W866 Fabyan Parkway Elburn IL 60119
- Bidder F. H. PASCHEN, S.N. NIELSEN & ASSOCIATES LLC, - $33,105,477, 5515 N. East River Road Chicago IL 60656
Apparent Low Bidder: PHEND & BROWN, INC.