We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Trench Shoring Company's Slide Rail Systems Meet Challenges of Fuel Tank Installation

Trench Shoring Company's Slide Rail Systems Meet Challenges of Fuel Tank Installation

December 1, 2016
ACP Staff
No Comments

Dealing with large-scale dimensions and unusual tank configurations presented multiple challenges in a recent fuel tank project at a Costco location. However, the specialized capabilities of Trench Shoring Company's Slide Rail Shoring System were more than equal to the task.

Because Costco sells so much fuel and must refill their tanks several times a week, the client required installation of five large fuel tanks, placed closely together. The contractor, Wayne Perry, also designed an L-shaped configuration for the large fuel tank installation pit, which measured approximately 60 feet by 70 feet. A key benefit of using an L-shaped design versus a traditional square configuration is reduction in both the labor involved in removing a larger amount of soil, plus the cost of expensive rock fill for such a large pit. Normally, such installations employ a square configuration because most companies are unable to handle shoring angles of such large scale. However, because considerable cost savings can result from pushing the limits of slide rail applications, B.L. Hayes Contracting, Inc. was hired by Wayne Perry to dig and shore the hole.

To provide the best solutions for this challenging installation, Mike Hayes turned to Trench Shoring Company to provide a component-based customized slide rail system. After fully understanding the contractor's specs for the Costco installation, Trench Shoring determined which components would best meet the multiple requirements. The company designed and delivered the equipment then assembled the system on the job site using Hayes' equipment. Because the Trench Shoring Slide Rails were pre-fabricated, there was no need to hire outside assembly labor, and welders, saving additional project costs. Total installation time was reduced as was lost time on site during the entire excavation and shoring process. Time from initial startup through the final grading of the hole to required depth was just four days.

Notes B.L. Hayes Principal, Mike Hayes, "I was very satisfied with the team we put together on this project. This was the smoothest install, due to Trench Shoring Company's on-time deliveries, extra rigging and lighter-than-the competition panels. Trench Shoring Company also provided a top-notch shoring installer, Jason Lakin, who was both knowledgeable and willing to devote the extra time needed."

 Wayne Perry and B.L. Hayes selected Trench Shoring Company because of their decades-long reputation and experience in handling large, difficult installations such as this five-tank fuel tank project. Trench Shoring Company is the largest supplier of patented slide rail shoring systems in the Western United States, providing slide rail panel sizes from 6 feet to 28 feet from their 10 locations. Because of the company's huge inventory, customized design support and fast delivery, and their commitment to the contractor's satisfaction, Trench Shoring Company has proven success in helping to keep projects on schedule and on budget.

Rocky Mountain Construction Projects
  • Related Articles

    Trench Shoring Company's Slide Rail Systems Meet Challenges of Fuel Tank Installation

    Pitsch Companies Discovers Benefits of Slide Rail Shoring System

    Trench Shoring Company Now Offers Composite Trench Covers for Driveways and Pedestrian Applications

  • Related Events

    Technical Webinar: Challenges and the Future of Construction Materials in Civil Engineering Projects

    AGC- Virginia - Richmond Legislative Meet & Greet

    ISA's 2018 LDA Meet & Greet

Write
ACP Staff

Lockheed Martin Invests $350M in State-of-the-Art Satellite Production Facility

More from this author

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing