We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.
ADOT&PF Completes $59M One-Of-A-Kind Airport Project

This unusual project presented a major challenge — there wasn't enough land for the extension.
ANCHORAGE, AL The Alaska Department of Transportation and Public Facilities (ADOT&PF) completes the $59 million Kodiak Airport Runway Safety Area Extension. This unusual project presented a major challenge - there wasn't enough land for the extension.
The solution -- build more land.
ADOT&PF, the Federal Aviation Administration (FAA) and project consultant HDR developed a plan to extend two federally required runway safety areas by 600 feet into the Gulf of Alaska and use engineered material arresting systems (EMAS) that will stop aircraft from runway overruns and undershoots.
The department then worked with Kiewit Infrastructure West to extend the safety areas and install two EMAS beds. This required creating a land base made up of about 14,000 armor stones, each weighing 12,000 pounds mined from a rock quarry 800 nautical miles away in Wrangell, Alaska. Each stone was shipped by barge to Kodiak, Alaska.
In total the project required:
2,400 concrete armor units
140-thousand tons of riprap
A million tons of gravel fill
"The entire project delivery team did a remarkable job with this challenging airport project," said ADOT&PF Commissioner Marc Luiken. "Kiewit's careful coordination of material delivery to this remote location and working closely with the airport's stakeholders, resulted in a superbly orchestrated safety project that will greatly benefit Kodiak and the U.S. Coast Guard Base."
The project was completed in less than 18 months for $59 million and was funded primarily through the FAA's Airport Improvement Program. The project also included building new taxiways and service roads to access the extended safety areas, airport lighting systems upgrades and culvert work.