We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Bertha Pushes Past Halfway Point in SR 99 Tunnel Dig

Bertha Pushes Past Halfway Point in SR 99 Tunnel Dig

October 28, 2016
ACP Staff
No Comments

SEATTLE, WA The State Route 99 tunneling machine Bertha has passed a significant milestone in its journey underneath Seattle, Washington. When the machine tunneled past Pike Place Market, it pushed beyond the halfway mark of a 9,270-foot-tunnel that will lead to the removal of the Alaskan Way Viaduct.

Seattle Tunnel Partners, the Washington State Department of Transportation's contractor for the tunnel project, has now excavated more than 4,635 feet of the SR 99 tunnel. Much of that progress occurred during the past five months, with STP tunneling more than 3,000 feet since leaving a planned maintenance stop on April 29 to begin the push beneath the viaduct.

Bertha is now about 190 feet beneath First Avenue between Pike and Pine streets. According to STP, crews will continue mining for a short time and then stop to perform approximately one month of planned maintenance.

"Bertha has been steadily on the move and made her way to the second half of the tunnel," Gov. Jay Inslee said. "This is good progress and I appreciate everyone's focus on making sure we safely complete this project."

That finish line - a 90-foot-deep receiving pit near Thomas Street, at the north end of downtown - is largely complete, along with many other aspects of the tunnel portals. Although future contractors will make final connections to the highway, several of the ramps and roadways into and out of the tunnel are already in place, along with tunnel operations buildings at each of the portals. New drone footage of Bertha's finish line is now available.

"This program turned a corner earlier this year," said Secretary of Transportation Roger Millar. "We're now closer to the end of the tunnel than we are to the beginning, and everyone on the team is working toward the day when the machine comes out the other side."

Other important work is ongoing, including construction of the double-deck highway within the tunnel.

While STP's crews are making progress, they are also taking time for routine maintenance to help ensure the machine successfully completes the tunnel drive. Like previous maintenance stops, crews will use the upcoming stop to inspect machine components and replace cutterhead tools in hyperbaric conditions. STP expects this round of maintenance to last approximately one month, but it could take more or less time depending on the extent of work needed.

STP's most recent schedule shows that tunneling will wrap up in summer 2017. Work to complete the tunnel's interior structures, along with installing and testing systems should be finished by late 2018. Based on STP's schedule, WSDOT estimates the tunnel would open to traffic in early 2019 when crews finish connecting the tunnel to the existing SR 99 roadways.

Pacific Builder & Engineer Projects
  • Related Articles

    Two-Mile-Long SR 99 Tunnel Opens in Seattle

    Bertha Breaks Through: SR 99 Tunneling Machine Emerges Near Seattle Center

    New Tunnel is Preferred Option for the State Trail at Mitchell Point in Oregon

  • Related Events

    Indiana Dig Law Best Practices

    AGC Maine Past Presidents Dinner

Write
ACP Staff

Lockheed Martin Invests $350M in State-of-the-Art Satellite Production Facility

More from this author

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing