We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Additional Track Arrives for DART Silver Line

Additional Track Arrives for DART Silver Line

September 12, 2020
No Comments
DALLAS, TX — A second delivery of rail for Dallas Area Rapid Transit's (DART) $1.2-billion Silver Line has arrived. Another 50 segments of new rail was recently off-loaded in Carrollton. The project's first 50 rail segments from Steel Dynamics, Inc. in Columbia City, Indiana, arrived July 15.

Construction Update

DART's design-builder for the 26-mile Silver Line Regional Rail Project, Archer Western Herzog, has been concentrating on the removal of abandoned rail along the right-of-way and utility relocation. They have also prepared 30 percent, 60 percent, and 100 percent design packages for civil, guideway, track, stations, bridge layouts, street modifications, and traffic control.

Overall, DART has received 281 of 436 total design submittals. With the arrival of the second load of rail, work moves into the heavier construction phase with an anticipated completion of the project and its 10 new stations in early 2023.

For the northern portion of its 13-city, 700-square-mile service area, an area currently seeing growth in employment, population, and activity centers, DART plans to use eight Stadler FLIRT trainsets ordered in June 2019.

DART is reviewing vehicle design packages including engine and cooling system performance reports and interior layout, and has received 150 of 164 total vehicle submittals. Vehicle design was completed in September 2020.

The Silver Line's equipment maintenance facility is currently at a 65 percent level of design. DART has forecasted the Silver Line at 5,630 daily boardings at the beginning of revenue service anticipated in March 2023.
Texas Contractor Projects
  • Related Articles

    Arrival of Rail for DART's Silver Line Keeps Project on Track

    DART Celebrates Silver Line Construction with First Concrete Pour Ceremony

    Richardson and Plano Get Silver Line Rail Delivery

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing