Contractual Dispute Resolution Provisions: A Primer

by: Jerry Negrete
Jerry Negrete
Jerry Negrete
Contracts often include a section titled ‘Dispute Resolution’ that lists terms such as ‘mediation,’ ‘litigation,’ or ‘arbitration.’ While contractors may have heard these terms before, it is my experience that most contractors are not comfortable defining each term, nor do they fully understand how each form of dispute resolution can impact a contractor’s ability to present and resolve project disputes. A basic understanding of the common forms of dispute resolution is crucial knowledge for any contractor.

This column will introduce the various forms of dispute resolution you may see in a contract. I will also provide examples of common dispute resolution contract provisions and discuss specifics to look for next time you review a contract.

Mediation
Mediation is a non-binding form of dispute resolution where the parties to a dispute meet, along with a mediator, to resolve the dispute. The non-binding nature means the mediator cannot reach a decision that is binding on the parties. Rather, the mediator provides his or her opinion on the strength and weakness of each party’s position and works to guide the parties to a mutually agreeable resolution. If the parties are unable to reach a resolution, the mediator will declare an impasse and mediation will end.

Contracts often describe mediation as a ‘condition precedent’ to litigation or arbitration. The AIA A201 includes the following mediation provision:

“Claims, disputes, or other matters in controversy arising out of or related to the Contract, except those waived as provided for in Sections 9.10.4, 9.10.5, and 15.1.7, shall be subject to mediation as a condition precedent to binding dispute resolution.”

This language does not change the non-binding nature of the mediation itself, instead it means the parties are required to participate in the mediation process before they are entitled to move onto litigation or arbitration.

Gomaco
Your local Gomaco dealer
Ring Power Corporation

When reviewing a mediation provision, contractors should consider where the mediation is to be held (project site, owner main office, virtually, etc.), how the parties select a mediator (mutually decided between the parties, the American Arbitration Association provides a list of potential mediators, etc.) and how the mediator’s fee is split amongst the parties.

Arbitration
Arbitration is a binding form of dispute resolution where a third party reaches a final decision that is binding on the parties. Arbitration has been a favored method of dispute resolution in the construction industry for some time. Unlike litigation in court, which can be very formal and limit the parties’ ability to determine who will reach a binding decision on the dispute, arbitration provides a more relaxed setting that enables the parties to select one or more arbitrators who have the requisite knowledge and experience to properly evaluate and decide a construction dispute.

The relaxed nature of arbitration also enables the parties to outline by contract what rules and processes govern the arbitration, and to affirmatively disclaim the application of other rules, such as the Texas Rules of Evidence. The EJCDC C-800 includes the following language regarding arbitration:

“All matters subject to final resolution under this Article will be decided by arbitration in accordance with the rules of the American Arbitration Association, subject to the conditions and limitations of this paragraph. This agreement to arbitrate and any other agreement or consent to arbitrate entered into will be specifically enforceable under the prevailing law of any court having jurisdiction.”

The AIA A201 includes the following language:

“If the parties have selected arbitration as the method for binding dispute resolution in the Agreement, any Claim subject to, but not resolved by, mediation shall be subject to arbitration which, unless the parties mutually agree otherwise, shall be administered by the American Arbitration Association in accordance with its Construction Industry Arbitration Rules in effect on the date of the Agreement. The Arbitration shall be conducted in the place where the Project is located, unless another location is mutually agreed upon. A demand for arbitration shall be made in writing, delivered to the other party to the Contract, and filed with the person or entity administering the arbitration. The party filing a notice of demand for arbitration must assert in the demand all Claims then known to that party on which arbitration is permitted to be demanded.”

Iowa Mold Tooling Co Inc
Your local Iowa Mold Tooling Co Inc dealer
Nichols Fleet Equipment

As you can see, arbitration provisions vary considerably. It is important to understand what requirements are included, and to note what is not specified. When reviewing an arbitration provision, contractors should note whether the arbitration is privately administered or administered through a governing body such as the American Arbitration Association, whether the arbitration is decided by one arbitrator or a panel of three arbitrators, where the arbitration is held, and whether the contractor is contractually bound to join in an ongoing arbitration regarding the same project.

Litigation
Litigation is a binding form of dispute resolution where a judge or jury reaches a final decision that is binding on the parties. Litigation in court is strictly governed by the Texas Rules of Civil Procedure and the Texas Rules of Evidence, as well as any local rules adopted by the specific county. Most jurors have never seen a construction dispute, and even those judges who have seen construction disputes do not generally have an intimate understanding of construction law. Therefore, contractors who find themselves in litigation have an obligation to use witnesses and advocates who can present the dispute and the governing law in an approachable way.

Because litigation is governed by strict rules, contractual provisions are generally short. The EJCDC C-700 simply states a party must “give written notice to the other party of the intent to submit the dispute to a court of competent jurisdiction.” The AIA A-Series documents include a checklist where a party can indicate the “method of binding dispute resolution shall be…Litigation in a court of competent jurisdiction.”

If a contract is governed by litigation, contractors should know if the contract requires suits to be filed in a specific county. Contractors should also understand if there is a waiver of trial by jury, which means a judge will reach the final decision instead of a jury.

Dispute resolution provisions may be full of ‘legalese’ contractors would prefer to ignore. However, these provisions contain critical information governing the path a contractor must follow to resolve a dispute. With this primer, contractors should be better able to discern binding and non-binding dispute resolution and suggest any changes in the dispute resolution process to better fit the company’s processes and preferences.

Wirtgen America Inc
Your local Wirtgen America dealer
Dobbs Equipment
Power Equipment Co
SITECH
Your local Trimble Construction Division dealer
SITECH Mid-South
SITECH South
SITECH Tri-Rivers
Wirtgen America Inc
Your local Wirtgen America dealer
Dobbs Equipment
Power Equipment Co