We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Crews Continue SR 24 Construction Project in East Mesa Area

Crews Continue SR 24 Construction Project in East Mesa Area

April 20, 2021
No Comments
PHOENIX, AZ — A project to add five miles of travel lanes to the Phoenix area's newest freeway is advancing in the southeast Valley with some of State Route 24's concrete pavement already in place.

The Arizona Department of Transportation's (ADOT) $77-million Gateway Freeway project will add an interim four-lane divided roadway between Ellsworth Road and Ironwood Drive when it is completed by fall 2022.

A stretch of SR 24 is now paved between Meridian Road and Ironwood Drive, near the boundary between Maricopa and Pinal counties. The paving is part of an initial phase to build the future intersection between SR 24 and Ironwood Drive. Current restrictions along Ironwood Drive are scheduled to wrap up by early this summer.

The project also is currently focused on the earthwork and drainage improvements. A fleet of large trucks and other equipment is being used to haul dirt to build embankments for bridges that will carry SR 24 over Ellsworth Road in an area close to Phoenix-Mesa Gateway Airport.

A drainage channel that will run parallel to the SR 24 extension on the north side of the freeway corridor also is under construction.

The first one-mile-long stretch of SR 24 between Loop 202 (Santan Freeway) and Ellsworth Road opened to traffic in May 2014. 

ADOT worked with the Federal Highway Administration and regional planners to arrange funding for the current SR 24 project as a way to provide drivers with a new route to ease local traffic demands — years ahead of when a full freeway could be built.
Rocky Mountain Construction Projects
  • Related Articles

    Parsons Wins ACEC AZ Grand Prize in Transportation for Central Mesa Light Rail Extension Project

    HALL Structured Finance Closes $17.3M Loan To Finance The Construction Of A Residence Inn By Marriott In Mesa

    Colorado DOT and Partner Agencies Celebrate Completion of US 24, CO 300 Project in Lake County

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing