We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Georgia DOT Provides Update to I-16/I-75 Interchange Improvement Project

Georgia DOT Provides Update to I-16/I-75 Interchange Improvement Project

March 16, 2020
No Comments
BIBB COUNTY, GA — Georgia Department of Transportation construction crews with the I-16/I-75 Interchange Improvements Project are moving forward with ongoing project items. Details of the project to date are below.

Phase 2 and 3 - Regarding the Region from Hardeman Avenue to the I-16 Eastbound Exit

Crews continue working on both the substructure and superstructure of the bridge on I-16 westbound over the Ocmulgee River. Crews continue work on retaining walls along I-75 northbound and southbound. Workers continued construction of the substructure of the Riverside Bridge over I-75, as well as the substructure of the new Walnut Street Bridge over I-75. Crews continue concrete paving alongside the new lanes of I-75 southbound between Riverside Drive and Hardeman Avenue. They have also started building concrete sound and visual walls along I-75 northbound and southbound.

Phase I - Regarding the Region Including I-16 from the I-75/I-16 Split to the Martin Luther King, Jr. Boulevard Exit

Crews continue the construction of the substructure for the new I-16 eastbound bridge over the Ocmulgee River, and continue working on the superstructure, or beams and deck for the bridge along I-16 eastbound near Spring Street. They are still building retaining walls along I-16 eastbound between Spring Street and Martin Luther King, Jr. Boulevard, as well as Martin Luther King, Jr. Boulevard near the Ocmulgee River. Crews have started grading on the Spring Street off-ramp from I-16 and on Martin Luther King, Jr. Boulevard near Riverside Drive.

Ongoing Long-Term Closures

  • The dedicated right turn lane on the I-16 eastbound off-ramp to Spring Street, which will remain closed through the spring of 2021


  • The permanent lane closure (for at least a year) on Coliseum Drive/Martin Luther King, Jr. Boulevard southbound between Clinton Street to Riverside Drive; southbound traffic in that area is currently reduced to one lane
Dixie Contractor Projects
  • Related Articles

    Georgia DOT Continues Work on I-16/I-75 Interchange Improvement Project

    Georgia DOT Focuses on Better Freight Movement with I-16/I-75 Interchange Reconstruction

    I-75 South Metro Express Lanes Critical Addition to Georgia Interstate

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2021. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing