We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Innovative Flex Lane on Madison Beltline is a First for Wisconsin

Innovative Flex Lane on Madison Beltline is a First for Wisconsin

Greater Flexibility on the Madison Beltline: Wisconsin DOT Utilizes First Flex Lane for Better Traffic Management on US 12

Crews remove a median barrier wall on U.S. 12, also known as the Madison Beltline, to make way for a new Flex Lane.
Asphalt paving takes place on the westbound Madison Beltline near Todd Drive.
Nighttime HMA paving operations take place near Todd Drive.
A concrete barrier wall is installed.
LCS, DMS boards on the eastbound Madison Beltline near Park Street.
A view of the Madison Beltline looking east from a pedestrian bridge near Park Street.
Median work takes place on the Madison Beltline at West Broadway.
A median barrier wall is shown near Stoughton Road.
August 9, 2022
Larry Bernstein
No Comments
Making the most of what you have is a cliché of positive thinking. However, it also is an apt way to describe a project from the Wisconsin Department of Transportation (WisDOT) – the Flex Lane on U.S. 12 in Dane County. The roughly 10-mile project area is located in Madison, Wisconsin. The average daily traffic count along the route is 120,000 vehicles.

Along the route, commuters have been experiencing significant backups, particularly during the morning and afternoon rush hours or when major events occurred in the area. WisDOT commissioned a traffic study about the best way to alleviate the traffic in the long-term. However, they were looking for an interim solution to help improve the traffic flow.

They decided on the Flex Lane. Also known as part-time shoulder use, it's a traffic management and operation strategy for addressing congestion, reliability, and safety issues. It involves using the inside median shoulders of an existing roadway for temporary travel during certain hours of the day.

On this stretch of U.S. 12 – locally known as the Madison Beltline – the left shoulder will serve as the Flex Lane. The six-lane highway has shoulders on both the right and left sides of the travel lanes.

It's projected that the Flex Lane will significantly improve travel time reliability and lead to an estimated savings of more than $11 million per year in user delay costs. In addition, the extra capacity is expected to reduce the number of crashes caused by the reoccurring congestion.

Creating Space

Previously, there was a double-run barrier wall separating eastbound and westbound traffic. There's also some space in between. To widen the left shoulder to 13 feet – a 10-foot travel lane and a 3-foot shoulder – the team ripped out the double run barrier, put in a single slope, and shrunk the driving lanes from 12 feet to 11 feet.

When open this summer, the Flex Lane will be available during weekday morning and afternoon rush hours, special events, or incidents. By restricting shoulder lane use to only the peak periods of travel, the full shoulder width is available during the other portions of the day for emergency stopping and recovery of disabled vehicles or debris.

To prepare the Flex Lane to be able to handle more traffic, crews reconstructed the concrete shoulder along with a 4-inch asphalt overlay.

Other work on the project included:

  • Resurfacing to address deteriorating pavement


  • Improving existing drainage facilities


  • Updating pavement marking


  • Installing changeable signage


The changeable message signs will be used to indicate when the shoulder is available for use.

Access On and Off

“The biggest challenge on the project was work zone access,” says WisDOT Project Supervisor Alex Hagen, who is overseeing the design and construction of the project. Most of the construction work was located in the median of U.S. 12, which is currently protected with a temporary precast concrete barrier wall. “Access to the median work zone was primarily achieved through nightly lane closures or during off-peak daytime lane closures.”

Another challenge the team has faced is the microchip shortage due to the global software chip shortage. The chips are required for the Lane Closure Signs (LCS) and Dynamic Message Signs (DMS). The LCS signs indicate red, green, or yellow to alert drivers about entering and exiting the Flex Lane while the DMS displays if the Flex Lane is in use and other messages.

The decision to open and close the Flex Lane will be made by staff at the WisDOT Traffic Management Center in Milwaukee. They will be able to decide with the cameras and traffic detectors that the team installed on the road.

“Because the system is dynamic, we can detect traffic counts and open and close the Flex Lane as needed,” Hagen says. The Flex Lane can be turned on in 20 minutes. Before turning it on, the team will work with local partners to make sure there are no obstructions on the lane and it is clear of debris. Closing the lane is straightforward – changing the LCS from green to yellow to red.

Testing, Testing

Serving as the prime contractor on the project is Payne & Dolan, Inc., which is part of the Walbec group. They have worked with WisDOT in the past. “They're very schedule driven and keep themselves and their subcontractors on schedule,” says Hagen.

The project began in March 2021 and was largely complete in December 2021. Due to a global software chip shortage, some 2021 work carried over into 2022, such as LCS and Dynamic Message Sign (DMS) installation. The Flex Lane is scheduled to fully open this summer. The Flex Lane is going through a testing phase before the opening.

The project was let for $45.1 million, but the total anticipated cost rose to $51.3 million. The bulk of the extra cost was a single change order. It involved building an auxiliary lane extension to improve overall mobility, operations, and safety for a 1-mile stretch of the Beltline. Funding for the project was split between the federal government, which picked up 80 percent, and the state, which picked up the remaining 20 percent.

WisDOT is evaluating potential long-term solutions for the Madison Beltline/U.S. 12 system. In the meantime, the Flex Lane will extend the remaining 10 to 15 years of life expected for the roadway while addressing existing safety and operational needs. Commuters will no longer regularly experience major backups during busy times. This is all because WisDOT is making the most of the available space.
Western Builder Projects
  • Related Articles

    New US-23 Flex Route Traffic System is First for Michigan

    AECOM Awarded Contract by the City of Madison to Design the First Municipal PFAS Treatment Facility in Wisconsin

    Oregon School District's Forest Edge Elementary is First Net Zero School in Wisconsin

  • Related Events

    AGC - South Florida -First Friday Luncheon

    AGC South Florida - First Friday Luncheon

Larryb
Larry Bernstein

Ohio DOT Partners With Kokosing on I-70/I-71 Downtown Ramp Up

More from this author

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing