We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.
Lacy Construction Completes Expansion at Barr Middle School
GRAND ISLAND, NE — Lacy Construction completes the remodel and expansion of Barr Middle School in Grand Island, Nebraska. The $12 million project for the Grand Island School District, involved the addition of 36,300 square feet of space and a remodel of the existing school building, which is located at 602 West Stolley Park Road.
Specifically, Lacy Construction updated the gymnasium with new basketball and volleyball courts, and installed a rubber floor system in both the gymnasium and nearby corridors. All rooms were equipped with new variable air volume (VAV) systems and Lacy added a three-level stair tower to facilitate safe egress in the event of a fire. Construction was completed in four stages to avoid disruptions and to ensure the safety of Barr Middle School’s students and staff.
In Lacy Construction's quest to find the best construction methods and materials, various innovative techniques and equipment were used on this project.
The large floors were all poured using the Ligchine screed, a concrete screed that ensured a fast, smooth and accurate application. The screed is guided by a laser leveling system that automatically adjusts 10 times per second and is capable of smoothing 10,000 square feet of concrete per hour.
Rather than spend extra time and money on demolition, Lacy also pumped an abandoned water line with grout instead of removing it, saving nearly $5,000 and about a week of construction time. Cardboard templates were placed in an existing radius stairway system as a low-cost method of determining the placement of decorative metal panels. The team also used a 36-inch diameter saw to cut through foundation walls and concrete canopies, leaving a clean finished surface.
For this project, the project team recognized the need to digitize its workflow, so they used the Submittal Exchange program by Oracle to manage all aspects of this complex job. All submittals, RFIs, ASIs, proposal requests, and punch lists were all distributed and electronically tracked through this system. Thanks to Oracle’s technology, the project team was able to save time, money and resources equivalent to 15.7 trees, 3,196 shipping days, and $26,754 of mailing expenses.
Most jobsites encounter challenges and this two-year project was not an exception.
The team was presented with numerous weather-related and scheduling problems. Its main concern involved student and staff safety. Circumstances required the team to perform most of its work during school hours, and maintaining a clean, quiet environment was paramount. Barr Middle School was able to accommodate the team by shifting classrooms into other parts of the building. The team focused on completing the largest portion of the addition first so the school could expand into the new space during the final phases of construction.
Lacy also utilized the school’s summer breaks and holiday vacations to remodel community spaces, such as the cafeteria and athletic locker rooms. Daily communication between the jobsite superintendent and Barr Middle School’s principal ensured these transitions would be as smooth as possible.
Nebraska’s notoriously bitter winters can provide serious temperature and moisture challenges on the jobsite. It is incredibly difficult to erect masonry walls in freezing temperatures therefore the project team overcame these weather-related issues by utilizing specialized scaffolding and poly tenting to enclose entire sections of the building. Heating units were also installed to maintain a constant temperature, allowing the walls to cure properly.
Despite best-laid plans, the team did encounter some unforeseen building conditions that threatened the schedule.
The school’s low ceiling heights, narrow clearances for plumbing and ductwork, floor conditions and asbestos were all problems that the team was able to overcome with constant communication and brainstorming between the Lacy team and its subcontractors.