The substructure of the new bridge is complete. Crews recently installed metal bridge deck forms that will eventually hold the concrete in place. Soil treatment and asphalt paving operations for the new alignment is underway. Other work in progress includes the installation of drainage structures and slope revetment.
The $42.2-million project was awarded to Key Constructors, LLC. Work is expected to be completed summer 2022.
All concrete corbels have been cut and beam end repairs are underway. Pile connection repairs are also underway. The $1.5-million project was awarded to Olympus Painting Contractors. Work is expected to be completed by summer 2021.
Additional work includes borrow excavation, channel excavation, beam placement, concrete pile driving, bridge deck work, and placement of erosion control devices. The existing roadway pavement and bridges within the project limits will be removed and the roadbed graded as needed to provide adequate drainage. The new alignment is also part of a proposed four-lane project on SR 19 from Tucker south to House.
| Your local Trimble dealer |
|---|
| Kirby-Smith Machinery |
| WPI |
| WPI |
| Kirby-Smith Machinery |
| Kirby-Smith Machinery |
| WPI |
The $11.7-million project was awarded to Joe McGee Construction Company. Work is scheduled to be completed by fall 2021.
The project was awarded to W.G. Yates & Son Construction Company. Work is currently expected to be completed summer 2022.
On the Cow Creek bridge, work consists of installing girder support plates, replacing mid-span diaphragms, installing new steel risers, abrasive blasting, painting of all structural steel and removing unsound concrete and replacing with epoxy mortar. Crews are currently blasting and prime coating the Cow Creek bridge.
The $2.9-million bridge preservation project was awarded to Gibson & Associates, Inc.. Work is on track to be completed by summer 2021.
Crews have placed all construction signs and erosion control measures. The widened section of roadway has been brought up to grade and the surface paved. Crews have also completed the widening of the north and southbound outside lanes, and have moved on to median work for Phase II.
| Your local Takeuchi Mfg Ltd dealer |
|---|
| Kirby-Smith Machinery |
| Kirby-Smith Machinery |
| Kirby-Smith Machinery |
The $2.6-million project was awarded to Walter’s Construction Company. Remaining work is on track for summer 2020 completion.
Remaining work includes spot milling and failed asphalt pavement repairs. The $3.3-million project was awarded to Dickerson and Bowen, Inc. and is scheduled to be completed this summer.
In Scott County, a $9.9-million mill and overlay project on approximately eight miles of I-20 eastbound from the rest area to the Newton County line is underway. Completed work includes the reconstruction of the Exit 96 mainline, failed pavement repair, edge drain installation, pressure grouting, and milling. Remaining work is on track to be completed this fall. The project was awarded to W.E. Blain & Sons, Inc.















































