We use cookies to provide you with a better experience. By continuing to browse the site you are agreeing to our use of cookies in accordance with our Cookie Policy. In addition, the California Consumer Privacy Act ("CCPA") provides certain rights with respect to your personal information. Please click here for more information.

Home » Interstate 90 Exit 37 Reconstruction Project Begins

Interstate 90 Exit 37 Reconstruction Project Begins

June 17, 2022
No Comments
STURGIS, SD — The South Dakota Department of Transportation (SDDOT) says the first phase of a four-phase project to reconstruct the exit 37 interchange on Interstate 90, near Sturgis, has begun. The project includes the reconstruction of the exit 37 interchange, eastbound grading on I-90, paving from west of exit 37 to the Tilford Port of Entry, drainage structure extensions, installation of pipe culverts, installation of a commercial vehicle electronic screening system, and the construction of a new port of entry building.

Phase one will include the construction of a center bent for the new bridge at exit 37 and grading of the new exit 37 westbound off ramp and eastbound on and off ramps. Phase one construction is scheduled for completion by July 27, 2022.

Phase two of the project is anticipated to begin August 15, 2022. Phase two work will include work in the westbound lanes and median of I-90 to replace drainage culverts, extend box culverts, installation of the commercial vehicle screening system, construction of the exit 37 westbound on and off ramps, continue with the construction of the new exit 37 overpass bridge (Pleasant Valley Road), demolition of the existing port of entry building, and begin construction of the new building.

Phases three and four will occur in 2023 and will include the replacement of drainage culverts and box culvert extensions, as well as grading and paving of the eastbound lanes on I-90 from west of exit 37 to the port of entry, completion of the interchange at exit 37, and completion of the new port of entry building.

The prime contractor on the $35-million project is Complete Concrete, Inc. of Rapid City. The project is scheduled for completion by October 27, 2023.
Western Builder Projects
  • Related Articles

    Interstate 90 Construction Beginning in McCook County

    I-90 and LaCrosse Street Interchange Reconstruction Adds Capacity to Keep Up with Growth in Rapid City

    State and Local Officials Celebrate the Early Completion of the Main Avenue Phase 2 Reconstruction Project

Post a comment to this article

Report Abusive Comment

Select a Region

See stories from other regions.

Select region map Select region map
ACP logo associated construction publications logo
  • About
  • Editorial Calendar
  • Archived Issues
  • Contact Us
  • Subscribe
  • Privacy Policy

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing

Copyright ©2022. All Rights Reserved
Design, CMS, Hosting & Web Development :: ePublishing